Monday, May 17, 2010

6. The pool goes in

The swimming pool shell is the first part of the building to go in, then the rest of the house and deck will be built around it. It was a very quick process, only taking four days from lines on the the ground to the concrete shell. 

Marked out...

The first bucket-load...

six hours later, the completed dig...

Formed up and steel 'reo' in place...

Concrete sprayed... 
Completed shell...

The formwork will come off next week, and that will be the end of the work on the pool until much later in the process when the plumbing will be completed, the interior lined and the 10 LED lights installed.

No comments: